We have an Outbound Delivery having multiple line items.

I have a couple of questions.

1). How may material doc numbers will be generated if I do PGI multiple times?

2). Can I have 5 different material docs if I post GI 5 times (Per line). Is this scenario possible?

Your inputs are valuable. Kindly revert

Thanks,

Shetty

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Each PGI will have one material document irrespective of line items . But multiple PGI's are not allowed per one delivery document .

Answers (2)

Answers (2)

Former Member
0 Kudos

yes , one GI document is created for each delivery regardless of the plant and storage location (WH). It does not depend on the number of line items , rather depends on the no of deliveries .

Regards

harry_wu
Contributor
0 Kudos

Hi,

1. For outbound delivery, you can only post GI for the entire delivery. It's not possible to post partial GI for each item.

2. Only for inbound delivery, it's possible to post partial GR when confirming transfer order.

Former Member
0 Kudos

Hi Harry

In my scenario, Outbound delivery having 5 lines.

I created TO a and confirmed TO for only 2 lines.

Now when I do PGI for outbound delivery, GI is done for only those 2 lines with confirmed TO

I will do the rest of GI again

In this scenario, what will happen? how many material docs are posted?

Thanks

Shetty

harry_wu
Contributor
0 Kudos
In my scenario, Outbound delivery having 5 lines.

I created TO a and confirmed TO for only 2 lines.

Now when I do PGI for outbound delivery, GI is done for only those 2 lines with confirmed TO

Have you done that in system? Is it allowed?