on 08-09-2010 3:12 PM
Hello
In cj20n im trying to automate the NWA assignments in the funds management to the NWA. Is there a way to have this process automated.
thanks
MAtt
Hi Matt,
I assume that automate means you would like to derive the funds, funds center, funded program, grant from the network activity. No need to input these values in the network activity.
For this you need to configure derivation rule/assignment in the transaction FMDERIVE based on the requirements from your customer business. Hope I answer your question. Please let me know if I am not.
Regards
Srinivasan Desingh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi thanks for the reply
But i need to automate this by making sure that the update funds management button happens thru some kind of custome program. if this does not happen i can't create a manual cost allocation (KB15N) document using the NWA because of error message that funds are not assigned to the NWA..
Thanks
MAtt
In the Project, click on a wbs and then click on the NWA.in tab 3 ACCOUNTING click on it and the funds Management buttons appears on the bottom. click on the funds management and a window displays with the funds, funds center and functional center. im trying to automate this process. Any suggestions
thanks
MAtt
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.