Hi experts,
Are there any reports to check if the availability control is active to the projects?
Best Regards,
Osmar Tardivo.
There is a work around...Use status selection profile which has AVAC system status...and you can use this in almost all the reports, assign it to WBS Element, and you will get the projects whose WBS Elements have AVAC
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is no report that I can see for multiple projects
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can Check Report S_ALR_87013561 - as Given By HEMANT VASKAR.
Other Methods are:
Check transaction: OPS9 (Budget Profile).
There Check "Activation Type " under "Availability Control". There can be 3 possibilities:
0 - Cannot be activated.
1 - Automatic Activation.
2 - Background Activation.
or
You can goto transaction: CJ31 (Display Original Budget).
Then Extras->Availability Control->Availability Control Info.
Regards,
Harsh Saxena
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check S_ALR_87013561
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.