Hi Experts,

We are planning the project in the tr. KP04, using the Planner profile WBS Planing in USD and VEF. Then with Tr. CJR2, I use the USD currency. In Report S_ALR_87013532 - Plan/Actual/Variance, Appears the amount planned, but the VEF currency, when it should be USD and show other amount to conversion USD. I can help with this

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Reporting currency most of the times is defaulted to controlling area currency. You can change this setting through RPP0, the setting is at user level.

Regards

Answers (1)

Answers (1)

Former Member
0 Kudos

The standard behavior for the Project Planning allow different currencys that you needs, independent of the base currency. In this case I chose USD and this its OK (Tx CJR2). However when I run the PS reporst, for example S_ALR_87013532 and CJi4, the system doesn´t do the conversion for the value of the base currency (actually is VEF), if not that show the value corresponding to USD in the field that should be in VEF, this it´s not correct.

Planned Amount : 1.595.156 USD

The Reports:

Val. Tl/Mon Soc.CO Moneda Soc. CO Val. Tl/Mon TR. Moneda Tr.

1.595.156 VEF 401.880,39 USD

It should be:

Val. Tl/Mon Soc.CO Moneda Soc. CO Val. Tl/Mon TR. Moneda Tr.

3.429.585,4 VEF 1.595.156 USD

How could I fix this?