on 08-06-2010 2:52 AM
Hi Experts,
We are using Block planning in PP-DS.
We have created Block basis definiton and assign Class to PPM.
Blocks are visible in DS planning board.
When we manually drag the order outside the block, we are able to do that.
But, I am expecting system must not allow order drag outside the block.
Am I missing any configuration/setting?
Is this feasible?
Regards,
Vipul
Hi,
Which scheduling strategy you are using while interactive planning in DS board?
What is action in case of scheduling error?
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I forgot to maintain Resource master >> Block >> Maintain Blocks >> Requirements view.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.