Hi all,
In SRM bidding process, I need the initial bid price and the final bid price, quantity before negotiation and after negotiation, PR or project number for that bid invitation number. Can anyone tell me where these are stored. Actually I want to know where the changed document log is stored.
Regards,
Asha
Hi Asha,
AFAIK there is no Project Number in Bidding Engine.
Until Quote versionning (SRM 6.0 ?), there is no other way than looking at change documents.
All changes are stored in change tables: CDHRD and CDPOS.
You can try to reuse FM BBP_CHANGE_DOC_GET_NEW.
Rgds
Christophe
PS: please reward points for helpful answers.