Dear All,

We need your help for this budget error issue .

Please find our case:

Total released budget of WBS - 2.5 crore

Commitment amount - 2.4 crore ( PO - 1.7 crore + PR- .7 crore)

Remaining order plan- 0.1 crore

Assigned budget - 2.5 core

We are getting budget error while creating PO against a purchase requistion , although there is sufficient commitment amount for that purchase requisition) in the WBS .

Even if we consider remaining order plan value as blocked budget , but still there is suffiecient budget in the form of commitment values of Purchase requistion , which should be available for creating PO against them.

We also tried to remove this Rem . order plan , but still in the budget report we get the same rem. order plan value.

Kindly suggest .

Regards,

Vishal

.

Accepted Solutions (0)

Answers (5)

Answers (5)

ashutosh_saraf
Participant
0 Kudos

Kindly check Tolerance limit for respective Controlling area.Also check the network type PS02 assigned in Network Profile.

Former Member
0 Kudos

Thanks for help.

Former Member
0 Kudos

Hi,

Please check whether Availability control is on Overall Release or Annual Release.

Regards,

Arul.

Former Member
0 Kudos

Also check the Tolerance Limit settings maintained for the Budget profile you are using.

Regards,

Gokul

former_member203108
Active Contributor
0 Kudos

Check whether the PR & PO values are same, you can get budget error if PO value is more than PR value.

Former Member
0 Kudos

Dear Sir,

Thanks for the answer.

As suggested by you , we found that the PO values are more than the PR values in some some cases , which we suppose is resulting into budget exceed error.

I will check & confirm .

Regards,