on 08-03-2010 7:31 AM
gurus,
can we restrict the wbs against date. ex:project start at 01.06.2010 n finish 30.06.2010 so basically i can restrict the wbs in between these day for wbs so that after then no po will be raised.
the only way is to use an exit on save of PO to check if the WBS dates are within the PO dates
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dates in Proejct defination and WBs is scheduling purposed only. Ss you cannot restrict business to raise PO or any actauls posting based on these dates. This is one of hte required functinality but I don't think as of now it is supported by SAP in any of the modules.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As per standard functionality you cannot restrict business transactions on WBSe based on dates. Rather you can control with Status Management.
Regards,
Arul.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.