cancel
Showing results for 
Search instead for 
Did you mean: 

Confirmation of material

Former Member
0 Kudos

Hi all,

when i am creating sales order.at schedule line material is not confirm.

i checked in MMBE material is showing enough.

i checked in material master also there is no safty stock.

block is there not due to credit management but normal block but after removing that block still material is not confirm.

where i need to check.there is any other setting in availability check..

regards

ajit jaiswal

Accepted Solutions (1)

Accepted Solutions (1)

former_member183879
Active Contributor
0 Kudos

Hi Ajit,

This is a very big question because there can be various reasons why the SLC is not confirmed.

Do you atleast have an unconfirmed schedule line with the requested delivery date ( To ensure that SLC determination is working)

Is ur scenario, a third party or made to stock or made to order?

Is it relevant for availability check or TOR or both?

If you explore the configurations for all of these , you will get an answer. You can also manually look at the lead times (Various dates to calculate the MAD) and check the material values /requirements as of that date.

Also you have to look at AC whether only backward scheduling is applicable or both backward and forward scheduling are applicable. All these things will influence the way SLC functions.

After looking into these things, if things are not working for you, please let us know.

Answers (0)