Hi experts

Please let me know the best approach of uploading old poject stuctures in system.

Is LSMW best or custom BDC?

In case of LSMW, is it works with recording method/

In case of BDC, what way the data file for different project objects can be prepared (pd, wbs elements, network, activities etc0.

Or is it required to upload seperately for object type?

Warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can use BDC's for upload of Project related objects. A BDC used to upload, say, WBSe can be coded in such a way it will accomodate structure of any hierarchy levels. Please consult with your ABAPer for this.

Regards,

Arul.

Former Member
0 Kudos

Thanks ARULALAN ST

My project structure is a mix of WBS and network activities.

Such case, can the BDC be build accommodating both all objects? if so, how to template the spread sheet to gather the project data?

Warm regards

ramSiva

Former Member
0 Kudos

Hi,

You have to use separate BDC s for individual objects. BDC's are flexible in the way that after doing yor recording, the coding can be modified to adapt uploading of objects with varying structure.

Regards,

Arul.

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

i have always used separate lsmw's for each object - it is easy to control errors that way

Former Member
0 Kudos

This message was moderated.

former_member203108
Active Contributor
0 Kudos

Please take help of your PS Consultant. or else search the forum, I remember Virendra replying to similar requirment long time back.