Hello,
We have upgraded our SRM System from 5.0 to 7.0 and we are also implementing Contract Management in the new upgraded server.
While doing the settings for the Workflow, we have selected the workflow framework for contract (BUS2000113) as process-controlled workflow and all the old objects like shopping carts (BUS2121) and (BUS2203) as application-controlled workflow.
We have also activated BC Set for Contract with automatic approval.
When we are creating central contract in SRM, system is giving this exception message:
Method: INITIALIZE of program /SAPSRM/CL_WF_BRF_TRACE=======CP
Method: INIT_BRF_TRACE of program /SAPSRM/CL_WF_BRF_MSG=========CP
Method: CONSTRUCTOR of program /SAPSRM/CL_WF_BRF_MSG=========CP
Method: INITIALIZE_BRF_MSG of program /SAPSRM/CL_WF_BRF_MSG=========CP
Method: /SAPSRM/IF_WF_RULE_CONNECTOR~EVALUATE of program /SAPSRM/CL_WF_BRF_CONNECTOR===CP
Method: /SAPSRM/IF_WF_RULE_CONNECTOR~EVALUATE of program /SAPSRM/CL_WF_SCHEME_PROVIDER=CP
Method: GET_SCHEME of program /SAPSRM/CL_WF_SCHEME_PROVIDER=CP
Method: GET_PROCESS_SCHEME of program /SAPSRM/CL_WF_CONFIGURATION===CP
Method: CREATE_PROCESS_LEVEL_SEQUENCE of program /SAPSRM/CL_WF_CONFIGURATION===CP
Method: CREATE_PROCESS_INSTANCE of program /SAPSRM/CL_WF_PROCESS_MANAGER=CP
Has anyone faced this before and did we do the config right. Can one system have both Application and Process controlled active?
Any help is highly apprciated.
Thanks, Yatin
Hi,
Please check you have copied BRF objects from client 000. It is one of basic customizing activities.
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Masa,
We have upgraded the existing server from 5.0 to 7.0.
Initially all the objects are selected for application controlled work flow. Now, while implementing Contract Management, we have Selected the BUS2000113 and choose "Process-Controlled workflow" and activated the BC set for automatic approval.
Can system support Application and Process controlled work flow for different objects. If it does not, is there a way I can switch the frame work back to Application Controlled workflow for the bus type BUS2000113.
Thanks, Yatin
Hi,
You should use the workflow either Application Controlled workflow (or) Process controlled workflow
You should not use both system will not accept.
Please check with your client and active any one ot them.
Since you are upgrading from SRM 5.0 to SRM 7.0 better use Application controlled workflow which ever they are using
Get the client approval
Regards
G.Ganesh Kumar