UD without result recording

Former Member
0 Kudos

Can I skip the step of result recording and only I want usage decision for some purchsed items?

Is it mandatory to do result recording?

Thanks

SD

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

No its Independent process.You can skip the RR & directly go to UD.Only thing is that you can not do the RR after UD made.

Former Member
0 Kudos

Please follow the following steps,

For the material for which . u dont want to do result recording and just do UD

1. When u assign inspection type to the material , just uncheck the follwing check box for inspection type

a) Inspection by Tasklist

b)Automatic Assignment

c) Check Char.

The advantage of this would be , that while doing UD u will not see any open characterstic pending for ur input.

Thus RED / BLUE color info could be avaoided

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

This can be possible but not for some PO else for all PO's where the material with QM view is maintained.

in Qa11 u simply save the save the UD, the system prompt u the waring messege ''confirming the result without resulting''.

U click ok & it will post the stock.