on 07-31-2010 7:12 AM
Hi Gurus
we are going to start one project by next month.For that we are finalizing wbs element etc.this project will be in separate plant.
but initial expenses like land acquisition,statutory expenses are already booked against cost center.now we want to transfer the cost in cost center in to wbs elements.I know this can be done via KB11N. But the problem is when i am transferring cost budget details in CJ31 are not updating.means there is no effect in budget (commitment,actual,assigned)
My client wants to update commitment,actual in CJ30 after cost transfer from cost center to WBS
Can anyone help me on this?
Thanks in advance.
Regards
Haran.
Hi Hari,
The expenses transferred to WBSE will be in the form of actuals which can be seen in "Assigned" tab of txn. CJ30.
As per my understanding costing is already carried out in your project & you have used it for budget generation & these actuals were not a part of earlier costing then you can manually update the project cost & copy it again as budget in CJ30.
I hope it will help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.