on 07-30-2010 2:03 PM
Hi all,
I get this warning when I try to stage materials for a production order:
WM staging of materials not completed for entire quantity
The system allows you to continue with the process but in the end you find that some of the materials are not staged and you may need to create regular TOs for them.
Can anyone suggest how I can fix this problem??
Thank you very much.
Solved. Confirm Control Cycles and Component Allocation in Routing.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check register "Transport", field "CompleteT ransfer Requirement" / "Complete trfr rqmnt" in following customizing path:
SPRO->Logistics Execution->Warehouse Management->Interfaces->Define Porduction->PP / PP-PI
Best Regards, Dirk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Please try setting the Complete material staging indicator for the PP interface via:
SPRO->Logistics Execution->Warehouse Management->Interfaces->Define Porduction->Whse Number --> For you warehouse, tick the complete matl staging indicator.
SAP helps do state that " When the system generates transfer orders for transfer requirements from production (PP), this indicator controls whether a complete staging of materials must take place. This means that the system must generate transfer orders for the total quantities of all items in the transfer requirement."
So hopefully, this should help.
Thanks,