on 07-29-2010 5:43 PM
Hi,
I copied all my DC's from a track 1 to track 2.
Track 1 has Sofware component ABC version 10 and Track 2 has Sofware component ABC version 20.
I followed this wiki to acheive this,
http://wiki.sdn.sap.com/wiki/display/JDI/StepbyStepguidetoMoveaDCfromoneSCtoanother
Everything got deployed fine in Dev system of Track 2. But now when I import the activities in Cons system, I cannot see any DC's deployed.
Import log shows successfull for all activities. Not sure why the DC's are not deployed in Cons system.
Also : I did not had cons system maintained in track runtime until now. I maintained cons runtime just before starting the import in Consolidation tab. Hope that is not causing a problem
Any idea of what should be next steps.
Thanks,
Yomesh.
SAP message is opened and SAP is looking into this issue
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Perhaps the deployments are stuck. You can use the TCS Deployer UI to investigate this. Have a look at http://help.sap.com/saphelp_nw70/helpdata/en/cf/9f4b04ae0948af8b1746afe22dda16/frameset.htm for more info.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pascal,
That was a helpful link. I think the deployments are stuck as I see following message in the log,
status = notification still not executed by CBS.
Need to dig deep to onderstand why is it not deployed. But why is Import status shown as success if it is not yet deployed.
Thanks,
Yomesh.