Dear Experts,
My client has created a project where a wrong profit center was assigned to a particular WBS. As a result of which while booking revenue end users picked up WBS based on name and while booking cost it was booked based on Profit Center, which was suppose to be linked to some other WBS.
eg. WBS 'A' was suppose to have PC1, while WBS 'B' was suppose to have PC2. But by mistake vice verse happened.
So in this case cost for WBS 'A' was booked against revenue of WBS B.
This is giving wrong picture while analyzing profitability.
Can you suggest some means by which we can correct this picture?
Thanks and Regards,
Manish
Suggested JV
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Take help from your FI consultant. It can be corrected by JV postings.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Manish,
There is only way of JV posting, you post a single JV for all the line items at a time with cumulative amounts against each WBS element, else you have to reverse all the transactions of the each WBSE and then change the profit center and post the transactions which a very hectic job.
Regards
Praveen