Production order date mish match between ECC & R/3

Former Member
0 Kudos

Production order date miss match between ECC & R/3

Back Ground 1:

1.Planned orders are created in APO (PDS EXISTS)

2.Planned order Basic Dates Match in APO& ECC

3.Planned orders converted to Production Order in R/3

4.Production order transferred from ECC to APO through CIF immediately

5.Calenders,Resources,Master Data in Sync between both the systems

6.I have checked the integration Profile between APO-> in global settings it looks good

7.Same strategy used in APO & R/3 for scheduling

Issues

1.The Production order dates don't match in ECC & APO ?

Back Ground 2:

1.If in the Routing we have operations 10,20,30,40,50,60,70,80,90,100

2.Only Operations which have run time are cifed to APO depending on Control key (ie operations :20 40 ,60) and scheduling relevent

3.Que time is maintained in Work center and work center is assigned to 10,20,30,40,60,90 operations

4.Operations are start - Finish relation ship

Issues

1.When all the operations are not cified to APO ,will the Basic dates match for Prod Order in ECC & APO?

2.How does the above work?

3.would APO use pds to calculate the lead time ignoring the basic dates send from R/3 for Production orders(Converted in APO)?

Please let me know if need to check some other config points

Your response is greatly appreciated

Thanks in Advance

Regards,

Kamala

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Please refer to SAP Note No. 143314 , 684356 ,423626 for details how order integration works and would like to mention following points...

- check trnansaction OPU3 ( field 'Adjust Basic Dates' )

- Check transaction //cp3 for inhounse production order

- and APO is the date/time-dominant system.

Rgs - Vikas