Dear experts,

The customer raises 2 requirements to reduce manual entry workload. To meet those 2 requirements, is it the only way to use enhancement, etc.? Any bad impact of that?

Requirement 1: Default expiry date in contract and scheduling agreement. The expiry date should be starting date plus 3 months.

Requirement 2: Default 8:00 in outbound delivery. You know, the system defaults 00:00 currently.

Accepted Solutions (1)

Accepted Solutions (1)

former_member183879
Active Contributor
0 Kudos

Hi,

For your requirements, enhancement is the only way. There is no impact on the system as such for the enhancements. If this is needed to streamline your business process, you can go ahead and enable it. This is a simple reqmt.