on 07-24-2010 7:01 AM
i have created ZDM order for Service Center.
let me know it's whole cycle from service center to end customer.
also tell HOW TO CANCEL SHIPMENT DOCUMENT.
Dear,
Please go through this process,
ME21N - create Order ---> VL10D Create delivery ---> VL02N - Goods Issue ---> start Shipment - VT01N (Attach delivery here) ---> create invoice - VF01 ---> Goods Receive - MIGO --> End Shipment - V02N.
If you want to delete shipment then reverse this all above process..
It will help you, as per my understand what you say..
Regards,
Sandip
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
MIGO is done on the base of delivery.
You can select Goods Receipt, outbound delivery = delivery no.
All the line of delivery will come in migo item level.
click on item ok for all the item then check it is there any error.
In last click on POST or Save.
It will update the stock in particular plant.
Regards,
Sandip