Workflow for released Task

Former Member
0 Kudos

Hi experts,

Does anyone know a workflow in cProjects that reminds resources to execute and notify released Tasks?

Thanks a lot,

CAMILO URIBE

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Problem solved.

Thresholds were implemented.

schneidertho
Advisor
Advisor
0 Kudos

Hi Camilo,

The workflow which you find in standard is e.g. TS 28700002 (Task Released). But this is send immediately when the task is released, not 2 or 3 days before it is due.

Alternatively you could use threshold values and alerting (see evaluations in cProjects). Or last not least a customer-specific program. But the two other possibiliies seem easier for me.

Best regards

Thorsten

Edited by: Thorsten Schneider on Jul 24, 2010 12:40 AM