cancel
Showing results for 
Search instead for 
Did you mean: 

Difference partially confirmed activities via CN22 and CN25

Former Member
0 Kudos

Dear,

Apparantly there seems to be a difference in the SAP logics in partially confirming activities:

when we partially confirm an activity using transaction CN22, the activity is not planned anymore..

however we we partially confirm an activity using transaction CN25, the activit is still planned (status = DSPT)

What is the standard SAP logic around this ? Why is their a difference? Should and can the difference be corrected?

rgds,

bert

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Bert

Can you clarify - what are you trying to do? DPST is a system status when you try to transfer the dates from forecast to Basic.

Wheras using CN22 you can confirm the activity - means whatever been planned -trying to convert into actuals of the work performed. The same can be done in CN25 but with one network activity. Collective (work)confirmation can be done using CN27.

Regards

PP