Requiest is ready for import again - yellow triangle.

Former Member
0 Kudos

Dear Gurus.

I am performing transport import in STMS, when option" Leave transport request in queue for later import" is UNCHECKED.

Inspite of this option, transport requests appears with status "request is ready for import again" and yellow triangle in STMS list

Why?

Regards

Vladimir

Accepted Solutions (0)

Answers (1)

Answers (1)

paul_power
Active Contributor
0 Kudos

Hi Vladimir,

please refer to the online help:

Choosing a Transport Strategy

http://help.sap.com/saphelp_nw70/helpdata/en/40/e42396853d11d3b48100609419f767/frameset.htm

If you have choosen

Mass transports

By default, the import option Leave transport request in queue for later

import is activated.

You have to change the transport strategy.

Regards,

Paul

Former Member
0 Kudos

Hi

Thank you.

I am choosing single transports only. And I am wonder, why imported transport is waiting for import again. instead of being finished with green check V.

Regards

Vladimir

Former Member
0 Kudos

Hello

Did you find out why this happens? I have the same issue in one system, and i have no idea why this is happening.

former_member189725
Active Contributor
0 Kudos

This is because you have kept the option checked "Leave Transport Request in Queue for Later Import"

Check this thread http://scn.sap.com/thread/836940  so that the default setting is changed and the option "Leave Transport Request in Queue for Later Import" is not selected by default.