Hi experts,
Following is my scenario.
I had created project & Network, I had assigned the WBS to the
activities and to that activities I had done the relationship & then I
had schedule the network.
Now I am going to CJ20N & scheduling at the project level using
bottom-up scenario.
Till this scheduling is OK but.....
Scenario1- Now I am changing the Network dates let it will be form 20/07/2010 to 15/07/2010 & then schedule the network.Now at the time when I am scheduling at the Project level, date at the project level i.e of the finish date is not changing, it remains the same.
Scenario2- Now I am changing the Network dates let it will be form 20/07/2010 to 25/07/2010 & then schedule the network.Now at the time when I am scheduling at the Project level, date at the project level i.e of the start date is not changing, it remains the same.
Is there any required config to be done.
Kindly please do the needful
Regards,
Gagan
Check WBS scheduling parameters under PS-> Dates-> WBS dates planning-> Define Parameters for WBS Scheduling and set it as network determine dates. Also check adjust basic dates indicator.
Also check the funtionalities shift dates/ reconcile dates under planning board in CJ20n.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi experts,
Following is my scenario.
I had created project & Network, I had assigned the WBS to the activities and to that activities I had done the relationship & then I had schedule the network (Forward Scheduling).Now I am going to CJ20N & scheduling at the project level using bottom-up scenario.
Till this scheduling(Start & Finish Dates) is OK but.....
Scenario1-(Preponed) Now I am changing the Network start dates, let it will be form 20/07/2010 to 15/07/2010 & then schedule the network. Now at the time when I am scheduling at the Project level using T code CJ20n, date at the project level i.e the finish date is not changing, it remains the same.
Scenario2 (Postponed)- Now I am changing the Network start dates, let it will be form 20/07/2010 to 25/07/2010 & then schedule the network.Now at the time when I am scheduling at the Project level using T code CJ20n, date at the project level i.e the start date is not changing, it remains the same.
Kindly do the needful.
Regards,
Gagan
Hi,
Could you please explain this,
Scenario1- Now I am changing the Network dates let it will be form 20/07/2010 to 15/07/2010
Is the start date 20/07/2010 and end date 15/07/2010? I mean i did not understand this.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.