on 07-19-2010 5:25 AM
Dear PS gurus,
why there is a difference in dates,CJ20N Latest finish 30/08/2010 where CN50N Latest Finish is 03/09/2010
Regards,
AHS
Hi
Clarify on which level you are checking the dates and Check whether your project
1) is the network activity relationship is properly defined.
2) is there any constraint in the network activity
3) been scheduled and saved.
In CN50N you will get the relavant information based on the workcenter defined in the network activity whereas in CJ20N - project builder - will get info relavant based on the hierarchy.
Hope this helps.
Thanks
PP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
where in CJ20N latest finish date equals 30.06.2010 (DD.MM.YYYY)
and
where in CN50N latest finish date equals 01.07.2010 (DD.MM.YYYY)
We do person assignment & CATA is background job.
in cn50n the system shows 2lines for each activity.
Act W/c Personnel nr work Latest Start Latest finish
0010 MDE 27.05.2010 30.06.2010
0010 MDE 15276 32 27.05.2010 01.07.2010
0025 EDE 27.05.2010 30.06.2010
0025 EDE 18415 12 27.05.2010 30.06.2010
0030 EDR 27.05.2010 30.06.2010
0030 EDR 14125 20 27.05.2010 08.07.2010
0040 HDB 01.07.2010 01.07.2010
0040 HDB 11575 2 01.07.2010 01.07.2010
solved. The dates in CN50N has two records for this network activity:
Removed the filter on Activity in CN50N, then got both records.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.