HELP V_V2 ATP

Former Member
0 Kudos

Hello Experts,

I created two sales order. The value of stock is zero.

I confirmed the dates of ATP. I created a purchase order. Example

SALES ORDER QTY SHIP DATE

140024379 50 23.07.2010

140024380 250 23.07.2010

Purchase Order QTY Deliv. DATE

4510005812 250 20.07.2010

The problem is, when I'm executing the V_V2 is not showing the values that will be confirmed.

Kind rehards

LF

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello LF;

The rescheduling report will not always show the result that appears in

the sales order. e.g. A sales doc item which is rescheduled but has a

header level credit block will show a confirmation in V_V2 but this

confirmation will not be updated in the sales order. The purpose of the

rescheduling results list is to show the best confirmation according to

the rules maintained in transaction OVZJ.

This functionality works the same in VA02. If you carry out an ATP check

in VA02 you will get the delivery proposal screen (As you have set E in

OVZJ). Here you have the possibility to select the delivery proposal

with partial deliveries on different dates. However if you look at the

schedule lines again, the partial deliveries have not been transferred

to the schedule lines as the complete delivery has correlated the lines

into one delivery date. This is the same thing that happens in V_V2.

V_V2 reports the result of the availability check according to OVZJ

rules, and then the delivery group correlation correlates the complete

delivery in the sales order.

This is standard behaviour according to your customizing.

I hope it can clarify your question.

regards

Ruy Castro

Answers (1)

Answers (1)

Former Member
0 Kudos

Thanks for your help.