on 07-16-2010 8:08 AM
Hi
We are process of changing the pricing procedure of the particular sales process.
In case of old open sales order after changing pricing procedure if i update it in VA02 mode then also ...it is not picking the current sales order ...
Again in case of sales order where deivery has been done ...for them while creating billing ...it is taking current pricing procedure so that there is a mismatch of sales order amount and billing amount .
Again while creating return order w r t old sales order ...it is taking current pricing procedure in return order instead of taking the original one ....
Pls advice how to rectify this problem .
Thanks in Advance
Regards
Mrinal
For information, you cannot change the pricing procedure which is already there in a sale order to a different pricing procedure. Pricing Procedure in Sale Order / Billing will always flow based on the assignment you maintained in OVKK. So in your case, if sale order and billing have a different pricing procedure, then check the field for Document Pricing Procedure both in VOV8 and VOFA where I feel, both are different and whatever you maintained in VOFA, for the same, OVKK assignment has also been made.
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Lakshmipati,
I told I am in process of changing pricing procedure .
Currently normal pricing procedure is configured in the system. Now business wants to change it in list price pricing procedure ( i.e base price with tax pricing procedure ) . And new pricing procedure has some extra automatic discount value also .
My question was
1) There is no change in open sales order ....IT is OK
2) But for sales order where already delivery has been done then after changing pricing procedure it is taking new pricing procedure so that ..sales value and billing amounts are getting different . How to restrict this .?
3)For return order also ...it is taking new pricing procedure ... How to restrict the same ?
Regards
MKC
Hi MKC,
Can you share your thoughts how you are able to resolve this issue just to brainstorm?
Lets say you have pricing procedures PO (Pricing procedure Old) and PN (Pricing procedure New)
As you know Sales area+ Customer PP + Doc Pricing Proce = Pricing Procedure
If you have already modified your determination to PN, But what you need is PO. So you need to change this determination back to old determination and complete your open business transactions. This works only for Billing docs and it doesn't work for your Debit memo as you dont know the sales docs relevant for Debit memo.
For Debit memo's, You may need to create a new Debit memo request with old pricing procedure determination.
Thank you
Kris
For applying new PP on your desired sales order...Try with re determination I cat in your sales order (provided you don't have a subsequent doc to it) or you have to do a fresh process cycle, starting from New sales order creation. And assign rejection reason sales order as change in PP.
Thanks & Regards
JP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Do you want new prices to be picked up or new pricing procedure ? For a new pricing, use pricing type B after clicking on Update button.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.