UD at operation level

Former Member
0 Kudos

Hi,

Is there any possibility in standard SAP for UD to be given in in-process inspection at each operation level of production?

Please answer.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

Very good work around suggested by Partha. Make a Qualitative MIC, Mark characteristic attribute and maintain a selected set ( May be with codes A and R for accepted and rejected respectively).

Discuss with ABAPer to make a table or report to capture that MIC value and treat that as UD at operation level.

former_member42743
Active Contributor
0 Kudos

You can use the functionality Operatoin Complete. This is available in 6.0, maybe a version earlier. Can't remember when it came in. You'll find the config set up under,

QM-->Quality Inspection >Resutls Recording>Make Settings for Operatoin Complete.

It will allow you to assign the selected set of UD codes to the inspection type/plant combination.

This functionality has not integrated functions in SAP at this time and is primarily information only. But you could use user exits at various points and custom programming to check that operations are complete before performing other actions in the system.

FF

Former Member
0 Kudos

Hi,

Usage decsion at operation level is not possibe in std SAP. But if your requirement is to capture the decision,operation wise, of quality inspector , you can treat that decision as a MIC in RR and make a report to show that UD code operation wise.

partha

Former Member
0 Kudos

Hi

No in standard , not possible. UD is given for the whole lot.