on 07-15-2010 10:44 AM
Hi,
I think I have a serious problem.
I have two companies (A and B), same Controlling Area.
I have created project P with WBS element: P1.
I have created a transport Order for a material (from B to A).
The account assignment category for this material in the transport Order is Q.
In B, I REALLY NEED to treat this material in invidual stock for project P1. This is why in material master (MRP4) I should mantain Indidual/Coll: 1 (Individual Requiremnts).
I know SAP Standard doesn't allow this:
"If a material managed in project stock is to be procured from another plant using a cross-company-code stock transport order, the indicator must be set to 2 (collective requirements) in the issuing plant because, in this specific context, individual project stock management is not possible in both plants."
but still I really need to treat this material in an invidual way during the whole process.
So I need to send this material from project stock for P1 in B to project stock for P1 in A.
I know it is possible to transfer this material from project stock to unrestricted stock in B and then send it to A, but this would change the moving average price, and it wouldn't work.
How should I solve this problem?
Thanks in advance.
Luis.
Edited by: LUIS ÁLVAREZ on Jul 15, 2010 11:46 AM
Hi Luis
Did you find the workaround? dont see a real answer to the question
thanks
Francisco Iglesias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.