on 07-14-2010 12:30 PM
Hi All,
We are at SRM7.0 and working on extended classic. After a confirmation is created in SRM, it is created in the backend ECC but the status of the confirmation is still showing as " approved" and not "posted in backend".
Please advise.
Thanks
hi,
check in SRM system -T.code: BD87
enter the partner system -ECC backend
Enter the date and execute
Check for the error message
Regards
G.Ganesh Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Run Clean_REQ_REQ_UP program in SE38
also u can schedule it
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.