on 07-14-2010 11:04 AM
HI Gurus,
I want to know How Requirement strategy come to APO through CIF? I mean to say what are the parameters to be maintained in R/3 to get it CIFed to APO as Requirement Strategy.
Thanks,
Denish
Answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Denish,
Can you try BADI /SAPAPO/SDP_RELSTRAT
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Denish,
You need to maintain strategy group in material master and CIF it to APO. Then requirement strategy will appear in product master. Please note only limited requirement strategies are possible in APO unlike ECC. Hence you may not get all strategies in APO.
Read:
http://help.sap.com/saphelp_scm70/helpdata/EN/47/9dd3a28b3b3c5ce10000000a421937/frameset.htm
Best regards,
Vaibhav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Denish,
The "Z" planning strategies are maintained independently on both sides in ECC and APO.
When transferring the material from R/3 to APO you have to code a mapping in the respective user exit.
Function Module Name: CIF_MATERIAL_PRODUCT_MAP which is called in CIF User Exit for Material transfer CIFMAT01 in ECC.
Hope this helps.
Regards,
Abhay Kapase
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.