Number ranges for budget in PS

Former Member
0 Kudos

Hi All

I want to use different number ranges in project systems for original budget entry CJ30, release of budget CJ32 and budget carry forward CJCO.

I went to the following path in IMG but there is only one number range for all types of budget.

SPRO-Project systems-Costs-Budget-Create Number Ranges for Budgeting

I dont know know how to assign different number ranges for the above mentioned budget entry.

Regards

ASIM

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

i don't think separate number range is possible

but you can see the budget type in CJI8 which gives all the necessary differentiation for reporting