Dear Expert,
Is it a proper way for SAP-PS(T-code, program , or other ways) to return all the un-allocate budget when a WBS element is closed?
Many thanx!
Atom
you can use CJ35 or CJ38 to return unallocated budget but you need to "unclose" the WBS first.
go to edit > status > close > undo to remove clsd status.
if you want direct tcode to allow return of budget despite closed status, i dont think that is possible since attributes system statuses cannot be directly changed.
you may need an exit to undo and reset closed status for budget transfer transaction but that would be to tedious to do.
also consider use of user status that has similar effects of CLSD system status but still allows budget return.
regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
return all budget where?
when the project is closed the project data should be frozen
this way I have a report that the budget was say 3000 and the actual was 2500
if I then return the budget (to wherever? - the budget would be 2500 against actual 2500
how can I measure the efficiency of the project manager - everyone will look good
wrong practice in my opinion
there should be no need to return budget, unless you are using IM when the possibility to use budget elsewhere is a scenario