on 07-14-2010 4:31 AM
Experts
We have a scenario
Customer service scenario.
Contract=>Sales Order=>Project WBS Structure for project management( mainly used for Planning Cost and Revenue and Budgeting purpose => Service Order ( wich actually collect the actual Cost ) and Settled to Project WBS element.
here the question - can we settle to WBS element as statistical and actually settle to contract or Sales order ?
Scenario 2.
Contract=>Sales Order=>Project WBS Structure for project management( mainly used for Planning Cost and Revenue and Budgeting purpose => Service Order ( wich actually collect the actual Cost & Revenue ) billing will be done throught RRB on Service order and then gets settle both Cost and Revenue to WBS element
here the question - can we settle to WBS element as Statistical and actual recevier is Contract or Sales order ?
for the above scenario do you have any other way of handling it.
Thx & Rgds, GNi
Hi
For both the scenario when PS is been used for Planning , Budgeting which is the collector/receiver from sales order and service order - why you want to maintain WBS as Statstical ?? What is the intension to make the WBS as stastical ??
Please note when the WBS / Project is made stastical - no settlment rule cannot be maintained -but can carry the actual costs which acts as receiver and costs cannot be redirected unless the costcenter is been referred.
If still you want to make stastical - you need to refer the costcenter in the control tab of the respective WBS.
Hope this helps.
Regards
PP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.