commitment budget

Former Member
0 Kudos

Hi all

I have created service PO against wbs of amount rs 1000/- . Then created entry sheet of taking quanty 0.8 qty amount 800/-.

In S_ALR_87013558 - report , actual consumption showing 800 but commitment budget showing ZERO. Due to this assigned value in cj31 or other report showing only 800 instead of 1000.

Availability control active on ++

what is the possibility?

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Did you tick delivery completion indicator in PO?

Former Member
0 Kudos

Hi,

Thanks for reply.

I checked PO. there is no tick delivery completion indicator in PO.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Is your Service entry sheet quantity same as PO Quantity? Check on the Quantity.

Former Member
0 Kudos

Thanks for responding.

Entry sheet qty is 0.8 and PO qty is 1

Former Member
0 Kudos

Hi Srikant ,

Check your Unit of measure .If it is other than AU than commitment will reduce on quantity basis & not on value basis.

Regards

Project Team1

Former Member
0 Kudos

Unit of measure for service po is EA(Each).

Former Member
0 Kudos

Hi Srikant ,

Kindly maintain your UOM as AU .

Regards

Projecrt Team1

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

Hi,

Check if commitments management is active in the system.

Regards,

Gokul

Former Member
0 Kudos

Hi

Thanks for your reply.

Commitment of other PO is showing in report.

Particullary for this and other two PO, remaining commitment after actual posting of cost showing ZERO.