cancel
Showing results for 
Search instead for 
Did you mean: 

First supply but sevrity is 400

Former Member
0 Kudos

Dear Experts

A inspection lot is raised based on GR purchases for a material for the first time with the vendor( the material also GRed for the first time).

But in QI -lot the severity is shown as 400 instead of 100.

What would be the reason.

Kindly explain

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Seviarity has nothing to do with the first lot or last lot,Its depend upon the sampling procedure you have selected (& what seviarity entered in sampling procedure) & Quality level you have.

If MIC contains the sampling procedure with the Seviarity 400 then it will be 400 till Quality level changes manually or automatically

I hope you understand

Answers (0)