cancel
Showing results for 
Search instead for 
Did you mean: 

Settlement Rule Report

Former Member
0 Kudos

Hi Expert,

Is there any transaction could list settlement rule and parameters for each WBS and Network / activity , the selection parameter would be project definition.

Best regards

Shubin

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor

Try these

Transaction Code Short text

KOSRLIST Collective Displ.: Settlement Rules

KOSRLIST_OR Internal Orders: Coll. Displ. SettRu

KOSRLIST_PP Prod. Orders: Coll. Displ. SettRules

KOSRLIST_PR Projects/Nets: Coll. Displ.SettRules

KOSRLIST_RE Real Estate: Coll. Displ. Sett.Rules

KOSRLIST_VB Sales Doc.: Coll. Displ. Sett. Rules

nitin_patoliya
Active Contributor
0 Kudos

Subin, mentioned Tcode will work out, I checked. By selecting chagne layout you will get all the requried details in this report.you have to create variant according to your requirement.

Tcode KOSRLIST_PR Projects/Nets: Coll. Displ.SettRules

Thanks Virendra for correcting me.

With Regards

Nitin P.

Former Member
0 Kudos

Thanks a lot to your all.

Closed .

Answers (1)

Answers (1)

nitin_patoliya
Active Contributor

I don't thnk such report is available.

One option could be RUn CJI3 based on limitation of Settlement cost element and Business Transaction KOAL/ KOAO etc. which is settlement trasaction and than go to settlmeent document and from ther you can check parameter.... But this anyway you can achieve in any of PS Maintenance trasaction.

Much reruired report but the same is not there in std. report.

With Regards

Nitin P.

Former Member
0 Kudos

Hi Nitin,

Thanks a lot !

The initial requirment is , user want to maintain the settlement rule on WBS or Activity, but he did not know which one is already maintained, so that he would like to have a clear view .

Is there any other way ?

Best regards

Shubin

nitin_patoliya
Active Contributor
0 Kudos

User alwalys check the same in CJ20n or any other PS maintenance transaction. Cj20n click on that object --> Ctrl +F3.

This will take you to the maintain settlment rule overview. Where you normally maintain it. ( So, before maintained they can check if you are not using settelement strategy and CJB1/ CJB2 ) etc.

There could be report development option also, but not sure of logic as of now.

With Regards

Nitin P.

former_member203098
Active Contributor
0 Kudos

hi,

depend on the system status setc user can create the settlement rule in the project.execute cns41 report for project status.

regards,