on 07-12-2010 7:54 PM
Hi experts
I am in SRM 5.0 classic scenario and I have a problem, I need replicate requisitions from R/3 to SRM and all shopping carts created must go to SOCO, but the system check availabilit of materials in R/3 and try to create reservations and do not go to soco.
How can I deactivate availability check and send all shopping carts to soco?
Thanks
Nilson
did you check the following customizing ?
(TR: SPRO
Supplier Relationship Management
SRM Server
Sourcing
Define Sourcing for Product Categories
In column:Sourcing, set value: 2 sourcing always carried out.
Regards
Lauren
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nilson
How the requisions are create din your system and how they are ordering
for example PM Order - as what item category - Stock or NON STOCK.
Upon the item category - STOCK OR NON STOCK
Purchase request or Reservations will be created.
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
now PR created means you can transfer to SRM or you can create a PO in ECC
if you have valid source of supply PO can be created in ECC without venturing to SRM .
since procurement profile set for your purchase request and this PR will be transfered to SRM as a shopping cart .
are you finding difficulty to transfer this PR to SRM - give more details.
since you are saying that you want to transfer this PR to SR means?
PM ORDER /PS ORDER/ APO DEMANDS determines PURCHASE REQUEST or RESERVATIONS upon the inventory configuration .
now you said the output came as Purchase request so it needs to be procured externally .
what is the item category of the purchase request ?
What is the problem are you facing to convert into SC or PO ?
Muthu
Hi Muthu
I am creating purchase requisitions in R/3 and transfering to SRM, but when shopping carts are creted in SRM availability checs are executed and if the quabtity iin stock in R/3 s higher than the quantity required , the shopping cart do not go to SOCO, i need deactivat it, all shopping carts must go to SOCO even if I have quantities in R/3 stock.
Thanks
Nilson
Hi
are you geting any error while transfering PR to SC?
Is SC created successfully.
what is the error in SLG1 -srm?
OR smq1 in ECC
can you see your shopping cart in the monitor sc transaction ?
PR to SC and PO only.
WHAT IS THE SETTING EXISTS IN define backend object systems?
any settings for reservations?
normally approve shopping cart ( PR) sits in the buyers cockpit
Define Objects in Backend System (Purch. Reqs, Reservations,
You perform this step only if you create your Materials Management documents in a backend system.
You specify the documents that are to be created in the backend system for a requirement coverage request.
The following documents can be created:
Purchase requisition
Purchase order
Reservation
I think settings might stops you.
But this decision is very importnat at business level and upon your business process.
Muthu