on 07-11-2010 12:13 PM
Hi Guru's
I am trying to explore the new concept WBS & Network Progress tracking.
WBSXPD
NTWXPD
I have checked in SAP Help also there is nothing for the same.
Please explain me how i can use this feature.
I guess with the help of this i can have deadline monitoring at activity level.
Hi PSUSER ,
The both transactions are similar as EXPD & COMPXPD, in deed they uses the same generic progress tracking codes. For the usage of the transaction is a question of the business requirement, if you need a event-based monitoring of the WBS or network activities.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Progress tracking is explained clearly in SAP Help. I would still recommend you to go through SAP Help patiently and check. Else you can search the forum for Progress Tracking. There are a lot of threads explaining the concept of Progress Analysis.
You can also check the note 516476 - Consulting note Progress analysis. Hope this helps.
Regards,
Gokul
Edited by: Gokul on Jul 12, 2010 12:53 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.