on 07-09-2010 9:22 PM
I have Srm 7.0 . my problem is the configuration of UWL.
when user logon the portal SRM do not to see theirs task.
in the help in portal check details the next error is display
Connector) :com.sap.portal.connectivity.destinations.PortalDestinationsServiceException:User is missing credentials for connecting to alias SAP_SRM. Contact your system administrator
I have rol srmadministrator and I can see the my task but all other user don't see nothing
some suggetions? Thanks
Hi Carsten,
I assume you weren't able to register the alias SAP_SRM as WebflowConnector as well, correct?
When you do the connection Test for the System in PCD, does it fail in Step 3?
If yes, please create a new system from template and use template Dedicated System (SAP_R3_Dedicated).
Enter all needed connections parameters and Systemalias SAP_SRM. Then perform the connection test again and register SAP_SRM as WebflowConnector.
Hope the answer is usefull for you, it worked for me (I used SAP_R3_Loadbalancing as template first and got the exact same error).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
You can check note 1133821, which suggests some tests when configuring UWL destination service.
Kind regards,
Ricardo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hill Ricardo.
I have reviewed the sap note obtained the next results.
version of Netweaver for component UWLJWF
sap.com UWLJWF 7.01 SP5 (1000.7.01.5.0.20090825161547) SAP AG SAP AG 20100429173712.
the Rfc test was succesfull connect. but my users follow with the problem missing credentials.