Dear Gurus,
My scenario is like this.We have Two Plants Say (HYDS) & (KOLS).
HYDS - > Sending Plant.KOLS - > Receiving Plant.
Receiving Plant KOLS consists of 4 storage locations.
Say For Example KCOM,KJAI,KVIZ,KAHM.
Actually route is determined Based on Transporter zone(which are nothing but Plant(HYDS) to Plant(KOLS)).
But my requirement is Shipment cost varies for different storage locations.So ShipmentCost should be determined from Plant(HYDS) To Storage locations(KCOM,KJAI,KVIZ,KAHM).
Kindly suggest Any Work arounds other than creating new plants for each storage locations.
Regards,
Udhay
In route determination system uses the TZ comes of shipping point/receiving point, not the tZ of the plant.
According F1 help in SPRO (SPRO > LE > Transportation > Basic Transportation Functions > Routes > Route Determination):
...
Routes are determined depending on the following criteria:
Country and departure zone (departure zone of the shipping point )
Shipping conditions agreed in the sales order
The shipping condition is defined in shipping point determination.
Transportation group of the material
Country and transportation zone (receiving zone) of the ship-to party
...
So, in this case you could use four different shipping points instead of four separate plants.
Regards,
Csaba
Edited by: Csaba Szommer on Jul 9, 2010 2:12 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.