on 07-08-2010 8:12 PM
Dear all,
I am creating Inbound Deliveries with AH ATP category.
But now I am facing another problem.
In the Non-Assigned Freight Unit in Tabular planning (/SAPAPO/VS01), all inbound deliveries that I've created in R/3 are being grouped in just one line, increasing (adding 1) in the Shedulling Lines Column.
For example:
PO: 1000001 / 10.000 kg
VL31n:
Inbound Delivery A: 100kg / 07.15.2010
Inbound Delivery B: 200kg / 07.16.2010
In TP/VS - Non Freight Unit view:
Freight Number Category Amb Shed Lines Weight
1000001 PO Memo 2 300kg
But, instead of this behavior I would like to see:
Freight Number Category Amb Shed Lines Weight
1000001-1 PO Memo 1 100kg <- related to Delivery A
1000001-2 PO Memo 1 300kg <- related to Delivery B
How can I create one Freight Unit foreach Inbound Deliveries, not grouping all inbounds deliveries in one freight unit?
Thanks again,
Thiago
Hi,
check the freight unit settings and other conditions ..
cheers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Thiago. I´ve the same problem
"In the Non-Assigned Freight Unit in Tabular planning (/SAPAPO/VS01), all inbound deliveries that I've created in R/3 are being grouped in just one line, increasing (adding 1) in the Shedulling Lines Column"
I´ve created a split rules for purchase order, this split rules ID is ok. But, when a I created the deliveries inbound from APO are being gruped in one line.
I don´t know how I can configure the split rule of ATP Categories "AH".
Best regards,
Martin