Optimization Profile in Production Planning and Details Scheduling PP/DS

former_member182449
Participant
0 Kudos

Dear APO Expert,

In optimization Profile in PP/DS can , Can i add new objective Function ?

Like Mackspan , Total Setup Time , Total Setup Cost etc...

Regards

Rami

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Rami,

SAP delivered the following as the standard

objective functions that are optimised

Makespan, total setup times, total set up

costs, maxiumum delay costs, total delay

costs, total mode costs etc.,

I dont think there is a way you can add extra

function into it. You can still try out for some

custom development if required critically for

your business

Regards

R. Senthil Mareeswaran.