Budget exceed issue is coming while doing MIGO.
WBS Budget uploaded: 532,000 (INR)
Commitments: 417,530.07 (INR)
Available: 114,470 (INR)
PO vaues:
Gross Price(PBXX): 9,297 (CHF)
Customs: 1,481.25
CVD-NO MODVAT: 1,383.22
ECS on CVD: 27.66
Sec ECES ON CVD: 13.83
ECS on Customs: 58.12
HECS on Customs: 29.06
IN ADC 752.08
Actual Price: 13,862.22 (CHF)
No Taxes.
As per exchange rate shown in the PO which is 30.12 the commitment amount is same as actual price.
Now while doing MIGO the error is coming as "WBS element, budget for fiscal year 2010 was exceeded by 16,014.08 INR"
Message no. BP604
What could be the reason.
Thanks in advance
Shubham
Shubham,
1st check is your project budget is annual type or overall type ?
If it is annual and your PO is created in year 2009 and now you are trying to post the MIGO whch is in 2010 definately system will give budget error if you have not done budget carry forward and not entered budget for yhe year 2010.
Also your PO is is in other currency than INR so while MIGO system will calculate the exhange difference by taking current exchange rate and not exchange rate rate at the time of PO creation.
In commitment only tax value which going to load on material will be added and other taxces which you are going to get back that tax value will be extra while doing the MIGO.
please check all this and revert.
pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check is there any excise duty, export compliance, taxes etc.. at the time of MIGO.
rgds, Aby
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
go to CJ30 or Cj37 & check the assign value on that is same as you assign value on budget report.
it might be higher.
reconstruct using CJEN & check whether it will be fixed..
Regards,
sam l
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Kindly check out any validation for the budget... Try it once again for making migo, if po is punched & released all the levels, then migo want to be done..... Check any other pos are there & about the tax code also....
regards
Raman T S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.