cancel
Showing results for 
Search instead for 
Did you mean: 

planned revenue in PS report for Value general contract not appearing

Former Member
0 Kudos

Dear all,

i am assigning the WBS element in my value contract general.I need to get this value reflected in the PS report S_ALR_87013542 in the planned revenue .i am not able to acheive this.i am using a service material with item cat TAD.

when i create a sales order type ZOT copied from standard order OR and assign the WBS element i am able to get the planned value in the above PS report.could anyone guide me how to get the same in value contract general.

thanking you,

Best regards,

R.Srinivasan

Accepted Solutions (0)

Answers (1)

Answers (1)

jpfriends079
Active Contributor
0 Kudos

Kindly do following checks

check your planning/Revenue profile i.e. OPSB whether revenue from Sales Order is ticked in that.

Also checkk if WBS is a billing element.

Check Tcode OLPE.

If problem, still persists, then refer following SAP Notes

- Note 96404 - VA01/21/41: No quotation value/order value/planned revenue

FYI - How does the planned revenue update for contracts work?

Contracts have customer quotation character - their planned revenues are reduced completely by the first contract release order.Since the value of the first contract release order does not correspond to the complete contract value in general, the planned revenue is consequently reduced.

Thanks & Regards