on 07-08-2010 8:14 AM
Dear all,
I have an issue with the transport leadtime of ship to 12345 which is supposed to be 1 day in a particular route and transit durationtime is mentioned as 1 day in route determination
but it is taking sometimes 1 day and sometimes 2 days ...
can you explain me
than ks and regards
venkatramana
Hello Venkatramana;
Please take a look the notes 547961 and 146829.
These note contains a list of frequently asked questions (FAQs) concerning shipment and transportation scheduling in the R/3 system (in brief: scheduling) and Process flow of route schedule.
I hope that tip can help you a lot.
Regards
Ruy Castro