on 07-08-2010 4:58 AM
when we try to delete PO, we get error message: item 001 Netwk Activity 3300012 0010 budget exceeded.
how to resolve the issue? thanks
Hi,
Please search the forum. There are lot of threads relating to the issue.
Best Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I search forum already, but I'm talking about deletion of PO. the existing solution like RKANB*, CJEN,CJBN didn't work, also we can't change budget and tolerance limit. thus no solution can be found in the forum.
also I 'm very curious about deletion of PO, because same line item in PR quantity is 2, total valuation is 300K. the PO quantity is 1
and PO net price is 50K, but when I delete PO, it tells me the budget exceed: 120K, in 87013533 report, commitment for this item is 23K, plan -overall and actual-overall are all zero.
I don't know how 120K is calculated. can you answer me? thanks
1st check the budget type annual / overall.
please confirm when your project is activated for availability control ? before creating PR and PO or after that ?
If AVAC is activated after creation of PR and PO then definately system will give error.
In your case RKANBU01 required to be execute for the related PO / project to resonztruct the commitment data.
Please check in CJI5 report for a/c assigned object is it there any other commitments are present.
regards,