on 07-07-2010 3:20 PM
Hello,
i have created a substitution. This works perfect for one wbs element but only for one wbs element.
Can i do this for more elemnts os over the whole project?
Thanks.
Best regards,
Timo
Edited by: Timo Renz on Jul 8, 2010 7:45 AM
This works.
I have to define a substitution in the project profile and set this substitution to automatically.
Thanks to all.
Timo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In addttion to, Also what is written in Susbstitution. I mean if you have defined logic based on WBS level than you need to extend that logic to other levels.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I guess this is possible. You can maintian a substitution based on your project profile. However it also depends on what all fields you want to substitute in the WBS element. In the project profile you can have automatic substitution set.
Please check this and revert. Lets also wait for others to comment.
Best Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Assign the substituation in Project profile(1st tab) in the configuration. Also check the indicator for automatic substitution.
This will make sure substituation is applied for all WBS elements of a project.
Regards,
Mahendra Dighe
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.