Hello ,

In an order with header billing plan dates that are value-based, the actual date is not transferred from the Project System (PS) milestone, even though the actual date of the assigned milestone was changed via transaction CJ20N.

We are repeatedly facing this error , I have applied Note number 1395078 but still once in a while I am still facing the issue

Regards

Muralidharan.S

Accepted Solutions (0)

Answers (1)

Answers (1)

jpfriends079
Active Contributor
0 Kudos

Check the following path in SPRO

IMG - PS - Revenue & earning - planned revenues - Automatic Plan Revenue cal - Maintain Billing Plan Settings

There, you use the billing plan to plan dates on a WBS element whose payment requests or invoices relevant to sales are to be sent to customers.

The system updates the planned revenue and planned payment receipts to the relevant WBS element. The planned revenue is updated using the revenue element stored in the planning profile for the work breakdown structure and using the financial item assigned to the revenue element.

You make the settings given below for the billing plan. To do this, you carry out the following steps:

- Maintain billing plan type

- Maintain date description for billing plan

- Maintain revenue element for billing plan

- Assign billing plan type to project profile

Hope this can assist you.