Hi,
When i am going to change BOM it gives warning message "Enter change number, BOM has history requirement"
But my problem is when i put any number in field of change number it is allowing me to change the BOM.
It should not be accept any number that are not created earlier in the system. It must have to accept change number that is created for the history requirement for perticular material. kindly give your input on this issue.
Atul
Hi,
This behaviour is normal, because it's a option in Engeneering Change Management Customising
You have just to change the properties of your Object Type Profile (field Mgtrec) linked to your CM Profile.
In this case, you can't change a BOM if this BOM is not added in the CM objects before....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Any input from the experts....................
pls help to solve thids issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.