Hi,

How to exclude any project from PS validation?

Thanks

Smile

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Use a different project profile and do not have automatic validation set there. Else modify the existing validation to exclude the new project profile.

Regards,

Gokul

Answers (1)

Answers (1)

shubham_kiyawat
Participant
0 Kudos

Dear Smile,

Can you please elaborate more, like how the validation is put, is it automatic activation or manual activation.

If it is automatic then change the customizing setting to manual. Then the validation will not come automatically and you have to always activate for all projects manually.

Thanks

Shubham

former_member256837
Contributor
0 Kudos

Hi Shubham,

Thanks! Validation is set as automatic. Do not wish to make it manual.

Smile

nitin_patoliya
Active Contributor
0 Kudos

Then there is not other way for project based exclusion of validation. You can chagne errors to warnning, but the same is also across projects.